Lake Hope
High Purity Alumina (HPA) Project | Western Australia | IPT earning 80%
Lake Hope is Impact Minerals’ flagship asset located ~500 km southeast of Perth in the Goldfields-Esperance region of Western Australia where the Ngadju people are traditional custodians of the land.
The company completed a pre-feasibility study in mid-2025 highlighting a project NPV10 of A$1.165 billion (with no by-product revenue), Capex of A$259m and potential Opex as low as <$US4,500 per tonne with by-product credit. Impact is now undertaking feasibility studies to further define the Lake Hope project economics.
HPA is a critical advanced material with 99.99%+ purity (Al₂O₃) essential for lithium-ion battery separators, LED lighting and semiconductor substrates. The global market is projected to reach US$15.8 billion by 2030 at ~20% CAGR.
Impact has focused on fast-tracking its entry into the HPA marketplace since entering the Lake Hope project joint venture.
Option to acquire 80% of Playa One Pty Ltd (Lake Hope resource & IP).
Maiden Mineral Resource
Positive Scoping Study — post-tax NPV₈ A$1.334B at 10,000 tpa.
Low Temperature Leach process breakthrough — 4N HPA (99.99%) produced at low temperature.
Mining Lease Application lodged.
A$2.87M CRC-P federal grant awarded (with CPC Engineering & ECU).
Maiden Measured Resource of 730,000 t at 25.8% Al₂O₃.
50% interest in Alluminous Pty Ltd (HiPurA® technology) acquired.
Positive PFS released — NPV10 A$1.165B, IRR 47.5%, Opex US$5,860/t, Maiden Ore Reserve 1.7 Mt.
80% stake in Playa One completed; DFS commenced.
Pilot plant construction is underway (CRC-P co-funded). Membrane Selective Technology (MST) integration advancing with ECU MRRC. Mining lease approvals and DFS progressing. Offtake discussions initiated.
Lake Hope HPA Project Update — CRC-P Year One Results
Membrane technology integration delivering promising early results across the HPA flowsheet; all PFS assumptions and financial forecasts confirmed unchanged since June 2025.
December 2025 Quarterly Activities Report
Bench-scale membrane crystallisation of SOP by-product achieved; Stage 1 residue test work commenced as potential feedstock for HiPurA® integration.
Target: Definitive Feasibility Study (DFS) completion, incorporating pilot plant results and offtake parameters.
Subject to DFS, financing and offtake: Final Investment Decision (FID) and construction toward first HPA production.